Proyectos de ley › 90.ª Asamblea General

HF 2569Murió al terminar la sesión · 29 de febrero de 2024

Relating to the improvement of United States highway 30, including prioritization by the state transportation commission and restrictions on associated use of eminent domain

Presentado por el comité Transportation (successor To Hf 230) de la Cámara

Temas:TransportationEminent domain

La misma legislación: SF 111, HF 230, HF 589

Dónde está ahora

  1. Hecho: Presentado23 de enero de 2023
  2. Hecho: Subcomité22 de febrero de 2023
  3. Hecho: Comité de la Cámara1 de marzo de 2023
  4. Hecho: Lo aprueba la Cámara29 de febrero de 202487–4
  5. Se detuvo: Comité del SenadoMurió al terminar la Asamblea General
  6. Sigue: Lo aprueba el Senado
  7. Sigue: A gobernador(a)
  8. Sigue: Firmado como ley

Murió al terminar la sesión La sesión de 2024 terminó el 19 de abril de 2024, la última sesión ordinaria de la Asamblea General. Los proyectos que no pasaron por ambas cámaras murieron. ¿Qué es el embudo (funnel)?

Qué contiene

Resumen con IA The state transportation commission currently creates long-term plans for Iowa's main roads. This new law would require the commission to prioritize improving U.S. highways. Specifically, they must plan to expand all two-lane parts of these highways into four-lane divided roads until the entire highway is widened. (Todavía no está traducido al español.)1

Lea la explicación oficial (en inglés)

Current law delegates to the state transportation commission duties to develop, coordinate, and annually update a comprehensive transportation policy and plan for the state. The commission is required to prepare, adopt, and publish a long-range program for the primary road system. The program is required to be prepared for a period of at least five years and is required to be revised, brought up to date, and republished at least once every year in order to have a continuing five-year program. This bill requires the commission to prioritize the improvement of United States highway and to include in its long-range program plans to expand all portions of the highway consisting of two-lane roadways to four-lane divided roadways until the entire length of the highway is made up of four-lane divided roadways.

Cambiado después por la enmienda H-8093; vea Enmiendas.

Texto completo del proyecto (en inglés)2

Senate subcommittee

Named March 5, 2024. It hasn’t reported yet.

Three legislators hear a bill first and recommend what the committee should do; it’s the best time to weigh in. How to take part

Nota fiscal

Resumen con IA This bill requires the State Transportation Commission to prioritize expanding United States Highway 30 into a four-lane divided roadway. The expansion is estimated to cost $1.500 billion during construction, with state construction costs coming from the Primary Road Fund. Additionally, annual maintenance for the project is estimated to cost approximately $1.7 million per year from the Primary Road Fund. (en inglés)3

Lea la nota fiscal (en inglés)

Description

House File 2569 requires the State Transportation Commission to prioritize the improvement of United States Highway 30. The Commission is required to include in its long-range program plans to expand all roadways to four-lane divided roadways until the entire highway is comprised of four-lane divided roadways. For the expansion of Highway 30, the Department of Transportation (DOT) is required to expend all reasonable alternatives before exercising eminent domain to acquire land that is a part of a century farm or residential real property.

Background

United States Highway 30 is a roadway that goes east to west across the continental United States, with approximately 331 miles running through Iowa.

The State Transportation Commission consists of seven members appointed by the Governor and confirmed by the Senate. The State Transportation Commission is responsible for developing, coordinating, and annually updating a comprehensive transportation policy and plan for the State, including preparing, adopting, and publishing a long-range program for the primary road system. The program is required to be prepared for a period of at least five years and is required to be revised, updated, and republished at least once every year to maintain a continuing five-year program. Currently, the State Transportation Commission’s long-range plan does not include plans for Highway 30. The 2022 State Transportation Plan can be found here.

In most cases, the DOT allocates approximately 80.0% of federal highway funding to larger projects. However, federal funding is between 50.0% and 60.0% of annual funding available for construction projects. Iowa is allocated a fixed amount of federal highway formula funding each year, and funding for Highway 30 expansion will use the same resources.

Assumptions

  • Two lanes will need to be added to approximately 120 miles, costing an estimated $6.7 million per mile.
  • Four-lane bypasses will need to be constructed for approximately 39.5 miles, costing an estimated $10.0 million per mile.
  • An estimated 16 interchanges will be needed, costing approximately $16.1 million each.
  • Construction costs are based on the current bid prices for the types of improvements listed above.
  • Construction costs will be funded by a combination of federal funds and the Primary Road Fund (PRF). Federal funding for Highway 30 expansion may pay for up to 80.0% of the construction costs. However, this will depend on the timing of the project.
  • Operations and maintenance will be funded primarily by the PRF and will cost approximately $1.7 million annually.

Fiscal Impact

The expansion of Highway 30 is estimated to cost $1.500 billion throughout the course of construction. Federal funding could cover up to 80.0% of the total cost, but this will depend on future budgeting decisions made by the State Transportation Commission. All State funding for construction will be provided by the PRF. Annual maintenance costs for the full 120 miles will be funded by the PRF and are estimated to be approximately $1.7 million per year.

Source

  • Department of Transportation

Cómo leer una nota fiscal4

Lo que cambia del Código de Iowa (Iowa Code)

Modifica§307A.2

Cómo funciona el Código5

Cabildeo

2 a favor · 0 en contra · 6 indecisos · Quiénes →

Family tree

Earlier and later bills are matched by wording or an identical title.

Tried before

This idea has been filed in an earlier General Assembly. None got through a chamber.

  • SF 198 Requiring the state transportation commission to prioritize the improvement of United Stat…
    89th General Assembly · In committee · same title
    Cleared committee

Similar bills this General Assembly

  • HF 614 Requiring the state transportation commission to prioritize the improvement of United Stat…
    91st General Assembly · Renumbered as HF 886
    Nearly identical

Matched by wording or an identical title.