Bills › 91st General Assembly

HF 2283Renumbered as HF 2682 · February 23, 2026

Relating to grid-enhancing technologies and reconductoring, including study and reporting requirements

Sponsored by Rep. Charley Thomson (R)

Topics:Business & economy

Same legislation: HF 2682

Where it is now

  1. Done: IntroducedFebruary 5, 2026
  2. Done: SubcommitteeFebruary 9, 2026
  3. Done: House committeeFebruary 18, 2026
  4. Next: Passes the House
  5. Next: Senate committeeFunnel: by March 20, 2026
  6. Next: Passes the Senate
  7. Next: To the Governor
  8. Next: Signed into law

Became HF 2682 → Its progress continues under the new number. Go to HF 2682 What’s a funnel?

What’s in it

This bill relates to grid-enhancing technologies and reconductoring. The bill defines terms related to electric transmission capacity, congestion, and grid-enhancing technologies. The bill requires each public utility or transmission company that owns or operates electric transmission lines in Iowa to prepare and submit by January 1, 2027, and every three years thereafter, a public study to the Iowa utilities commission (commission) examining the feasibility of projects using grid-enhancing technologies and identifying reconductoring opportunities.

Read the full explanation

The bill requires the study to provide information on feasibility, costs, implementation time, and other information deemed relevant by the commission. The study must be designed to identify projects that can achieve one or more specified purposes, including increasing transmission capacity, reducing congestion, reducing curtailment of renewable and zero-carbon resources, improving reliability, reducing siting conflicts, increasing flexibility to reduce risks surrounding technology, reducing line losses, increasing flexibility in transmission planning, and improving the ability to serve new customers or increased customer load. The bill does not apply to a municipal utility, a cooperative electric association, or a company or organization that owns a transmission line that serves a single customer or interconnects a single electric generating facility. The bill allows public utilities and electric transmission line companies to rely on existing analyses and information developed by a regional transmission organization or its subgroups to satisfy the study requirements and to include that information as necessary.

From the explanation printed with the bill as introduced, written by the Legislative Services Agency. Amendments adopted later aren’t reflected. Full bill text

House subcommittee

Named February 9, 2026. On February 17, 2026 it recommended passage.

Three legislators hear a bill first and recommend what the committee should do; it’s the best time to weigh in. How to take part

1 written public comment to its subcommittee: February 17, 2026 (1) · on the Legislature’s site

Iowa Code it changes

Creates§478.34

Read from the bill as introduced. Each links to every bill touching that chapter of the Iowa Code. How the Code works

Lobbying

10 for · 0 against · 11 undecided · Who →

Family tree

Where this legislation came from and where it went: earlier tries, the versions it moved through this Assembly, and later bills built on it.

Earlier and later bills are matched by wording or an identical title; check the text to be sure it’s the same idea.