Proyectos de ley › 91.ª Asamblea General
Relating to matters under the purview of the economic development authority, the utilities commission, and the department of education, including creation of the headquarters expansion and development for growth and employment program, and the business incentives for growth program training fund; repeal of the new jobs tax credit program; the major economic growth attraction program; load forecasting and analysis of electric transmission system expansion plans; creation of the electric transmission system expansion planning and analysis and load forecasting fund; the industrial new jobs training program; establishing the new jobs training program interim study committee; the research activities credit; and including effective date provisions
Presentado por el comité Ways and Means (successor To Ssb 3103) del Senado
Proposed by the Economic Development Authority · all agency proposals
Temas:Business & economyEnergy & utilitiesTaxesTax credits & incentivesUtility rates
Dónde está ahora
- Hecho: Presentado12 de febrero de 2026
- Hecho: Subcomité18 de febrero de 2026
- Hecho: Comité del Senado12 de febrero de 2026
- Hecho: Lo aprueba el Senado3 de mayo de 202641–0
- Se saltó: Comité de la CámaraSe saltó
- Hecho: Lo aprueba la Cámara2 de mayo de 202678–7
- Hecho: A gobernador(a)13 de mayo de 2026
- Hecho: Firmado como ley2 de junio de 2026
HF 2799 se hizo ley → La misma legislación se aprobó como HF 2799, así que esta versión se dejó de lado. Ir a HF 2799 ¿Qué es el embudo (funnel)?
Qué contiene
Resumen con IA Este proyecto de ley crea un nuevo programa que otorga créditos fiscales a las empresas que amplíen sus sedes y contraten a más empleados en Iowa. También establece un fondo para ayudar a las empresas a pagar la capacitación laboral y cambia la forma en que funcionan algunos programas económicos existentes. Además, el proyecto de ley requiere que Iowa State University estudie las necesidades futuras de electricidad y ordena a las compañías eléctricas ayudar a pagar estos informes.1
Lea la explicación oficial (en inglés)
This bill relates to economic development authority programs and tax credits; load forecasting and the state electric transmission system expansion plans; and the industrial new jobs training program. DIVISION I —— HEADQUARTERS EXPANSION AND DEVELOPMENT FOR GROWTH AND EMPLOYMENT PROGRAM. The bill creates a headquarters expansion and development for growth and employment program (EDGE program) to provide tax incentives to eligible businesses. The qualifications for an eligible business, and the factors the economic development authority (authority) shall consider in determining if a business is eligible to participate in the EDGE program are provided in the bill. Applications for the EDGE program shall be submitted to the authority. The terms of, and aggregate value of, a tax incentive may be negotiated between an eligible business, the authority, and the board comprised of members of the authority appointed by the governor (board). An eligible business that is approved to participate in the EDGE program shall enter into an agreement with the authority specifying the criteria for successful completion of the program requirements. The requirements for the program agreement are detailed in the bill, and the authority may enforce such requirements. If the authority enters into an agreement with an eligible business, the authority may authorize a qualifying wage tax credit for the eligible business for a period not to exceed three years as specified in the agreement. The authority may issue a qualifying wage tax credit to the eligible business for each year of the authorized period upon verification that the eligible business employed the required number of employees in new corporate jobs and retained corporate jobs that pay at least 200 percent of the qualifying wage threshold. The tax credit for each year of the authorized period shall equal no more than the amount specified in the bill. A taxpayer shall include a tax credit certificate issued by the authority with the taxpayer’s tax return to claim the tax credit. An individual may claim a tax credit on behalf of a partnership, limited liability company, S corporation, estate, or trust electing to have income taxed directly to the individual in an amount based upon the pro rata share of the individual’s earnings. Any tax credit in excess of the taxpayer’s liability for the tax year is refundable or may be credited to the immediately succeeding tax year. Tax credit certificates are not transferable. The authority may prohibit an eligible business that receives a tax incentive from the program from receiving any other tax incentives or financial assistance under any program administered by the authority. Under the bill, individual and corporate income taxes, financial institution franchise taxes, and money and credits taxes on credit unions shall be reduced by a qualifying wage tax credit. DIVISION II —— MAJOR ECONOMIC GROWTH ATTRACTION PROGRAM. The bill amends the definition of a “foreign adversary” under the major economic growth attraction program (MEGA program).4(a) at any time from March 4, 2024, through the termination of the program.4 at any time from July 18, 2024, through the termination of the program. Under current law, the board shall not authorize tax incentives available under the MEGA program, or an exemption to restrictions on agricultural land holdings, for more than two eligible businesses, or on or after January 1, 2027, whichever occurs first. The bill extends this provision to January 1, 2030. DIVISION III —— BUSINESS INCENTIVES FOR GROWTH PROGRAM TRAINING FUND. The bill creates a business incentives for growth program training fund (fund) in the state treasury under the control of the authority.5 percent of the gross wages an eligible business pays to employees specified in an agreement with the authority shall be credited to the fund from the withholding payments made by the eligible business. Such jobs shall be identified by the authority as having a sufficient economic impact to warrant assistance with training. On a quarterly basis, an eligible business shall disclose the amount of gross wages that qualify to the authority and to the department of revenue (DOR). The authority shall calculate the amount of gross wages to be deposited into the fund, and the DOR shall deposit that amount into the fund. Moneys in the fund shall be used to reimburse training expenses incurred by an eligible business that are associated with the eligible business’s project, and that meet the requirements detailed in the bill. An eligible business that has been approved to receive a reimbursement from the fund shall not receive any other state incentives for the same purpose. DIVISION IV —— REPEAL OF THE NEW JOBS TAX CREDIT.11A.48(3)(e)(7). This division of the bill, being deemed of immediate importance, takes effect upon enactment. DIVISION V —— LOAD FORECASTING. The bill relates to load forecasting and analysis of electric transmission system expansion plans. The bill directs the authority to commission Iowa state university of science and technology (ISU) to produce a report forecasting the probable future growth of electricity use within the state and within the midwest region. The report must include a load forecast and an analysis of electric transmission system expansion plans, and must be commissioned from ISU at least once every two years. In developing the report, ISU must solicit input from residential, commercial, and industrial consumers and the electric industry. The published report shall only rely on information provided by utilities in aggregate form and must exclude any identifying information about an individual utility’s electric system. The load forecast and electric transmission system expansion planning analysis must be published by December 31, 2028, and biennially published on or before December 31 thereafter. The authority may commission other reports as necessary to evaluate energy needs. A report shall be made publicly available on the authority’s internet site. The bill grants the Iowa utilities commission (commission) authority to compel public utilities to share with ISU the utility’s information necessary to develop the load forecasts and electric transmission system expansion planning analysis required under the bill. A public utility may use a third party to prepare such information to be shared with ISU and may enter into a nondisclosure agreement with ISU requiring shared information be kept confidential. The bill also provides that the load forecast and electric transmission system expansion planning aggregate analysis may be used as evidentiary support in any proceedings before the commission as detailed in the bill. This authority to compel includes all electric utilities, including electric public utilities with few customers, electric cooperative corporations and associations, and municipally owned utilities.02 percent of the utilities’ total gross intrastate operating revenues from the prior year. Moneys in the fund are appropriated to the authority for the purpose of commissioning the load forecasting report and analysis. The bill directs the commission to establish by rule an aggregate maximum amount of remittances and a schedule for remittances. The remittances are in addition to assessments otherwise permitted and may be included in budgets approved for energy efficiency implementation as detailed in the bill. DIVISION VI —— IOWA INDUSTRIAL NEW JOBS TRAINING PROGRAM. Under current law, payment of program costs shall not be deferred for a period of more than 10 years from the date of commencement of the project. Under the bill, for an agreement entered into on or before June 30, 2026, payment shall not be deferred for more than 10 years and may not be extended, and for an agreement on or after July 1, 2026, payment may not be deferred for more than 5 years. A community college and an employer shall notify the department of workforce development upon entering into the agreement. Under the bill, a project shall not be funded unless the department of workforce development approves the agreement within 30 days of receipt of notice of an agreement. The bill requires a community college that receives a new jobs credit from withholding to annually report a detailed accounting of the community college’s bond interest. Under the bill, to be eligible for the new jobs credit from withholding, a community college most document that program costs are incurred over the period of time specified in the agreement with an employer, that program costs are not incurred to reimburse travel, conferences, or legal fees, and that administrative expenses do not account for more than 15 percent of the program costs. DIVISION VII —— IOWA INDUSTRIAL NEW JOBS TRAINING PROGRAM INTERIM COMMITTEE. The bill requests the legislative council to establish an interim study committee to review the new jobs training program and make recommendations regarding the program. Membership of the interim study committee, and the responsibilities of the committee, are detailed in the bill. The interim study committee shall submit a report detailing the findings and recommendations to the general assembly by December 15, 2026. DIVISION VIII —— RESEARCH ACTIVITIES CREDIT. The bill clarifies, for a research credit based on conducting agriscience research, which sections of the Internal Revenue Code apply and what claims a business is allowed.
Por qué importa. Las empresas elegibles podrían recibir créditos fiscales por expandir sus sedes y crear nuevos empleos corporativos, mientras que un nuevo fondo de capacitación reembolsaría ciertos gastos de capacitación empresarial. El proyecto de ley también extiende el plazo para ciertos incentivos fiscales bajo el programa Major Economic Growth Attraction y ordena a Iowa State University producir informes sobre el uso futuro de la electricidad y los planes de transmisión. Se estima que estos programas disminuirán los ingresos del General Fund en $1.8 millones en el año fiscal 2028, $1.9 millones en el año fiscal 2029, $3.9 millones en el año fiscal 2030, $2.0 millones en el año fiscal 2031 y $4.1 millones en el año fiscal 2032.2
Cambiado después por las enmiendas S-5259, H-8480; vea Enmiendas.
Texto completo del proyecto (en inglés) · Qué cambió antes de aprobarse3
5 comentarios públicos por escrito a su subcomité: 4 de marzo de 2026 (4), 11 de febrero de 2026 (1) · en el sitio de la Legislatura
Nota fiscal
Resumen con IA This bill establishes new tax incentives to attract corporate headquarters and large capital investments, extends the Major Economic Growth Attraction Program, and creates a training fund for business growth. These programs are estimated to decrease General Fund revenue by $1.8 million in fiscal year 2028, $1.9 million in fiscal year 2029, $3.9 million in fiscal year 2030, $2.0 million in fiscal year 2031, and $4.1 million in fiscal year 2032. Additionally, the extension of the Major Economic Growth Attraction Program is estimated to decrease General Fund revenue by $18.0 million in fiscal year 2030 through $18.7 million in fiscal year 2034 and decrease the SAVE Fund by $0.5 million each year during that period. (en inglés)4
Lea la nota fiscal (en inglés)
Description
House File 2799 relates to State economic development activities. The Bill has six divisions. Division I — Headquarters Expansion and Development for Growth and
Employment Program
Description
Division I of the Bill establishes the Headquarters Expansion and Development for Growth and Employment (EDGE) Program under the Iowa Economic Development Authority (IEDA). The EDGE Program provides tax incentives to attract and keep corporate headquarters in Iowa. The Program may provide the following incentives:
- A qualifying wage tax credit of up to 15.0% of the gross annual wages of new corporate jobs for up to three years.
- A qualifying wage tax credit of up to 1.0% of the gross annual wages of retained corporate jobs for up to three years, not to exceed $1.0 million.
Qualifying wage tax credits can be claimed against personal income tax, corporate income tax, franchise tax, and the moneys and credits tax. Any tax credit in excess of the taxpayer’s liability is refundable or may be credited to the immediately succeeding tax year. The Division allows the IEDA to establish an application fee and set requirements for the EDGE Program in administrative rules.
Assumptions
- One new headquarters agreement and one retained headquarters agreement will be reached every two years.
- Tax credits and agreements under the EDGE Program will last three years.
- The first agreements will be reached in FY 2027 with the first claims occurring in FY 2028.
- It is assumed that one-third of an awarded EDGE Program tax credit will be claimed each year.
- Tax credit awards for new corporate jobs will be 15.0% of the gross annual wages of the jobs.
- Tax credit awards for retained corporate jobs will be 1.0% of the gross annual wages of the jobs.
- Wages will increase by 3.0% each year.
- The average headquarters employs 255 employees, and 30.0% of employees meet qualifying wage requirements.
- The average qualifying wage in FY 2026 is assumed to be $140,000.
Fiscal Impact
Division I of the Bill is estimated to decrease revenue to the General Fund by the following amounts:
- FY 2028 = $1.8 million
- FY 2029 = $1.9 million
- FY 2030 = $3.9 million
- FY 2031 = $2.0 million
- FY 2032 = $4.1 million
Division II — Major Economic Growth Attraction Program
Description
Division II of the Bill extends the end date of the Major Economic Growth Attraction (MEGA) Program from January 1, 2027, to January 1, 2030. The Division also modifies the definition of “foreign adversary.”
Background
The MEGA Program provides tax incentives to attract capital investments from businesses that invest at least $1.000 billion in the State. The business must be primarily engaged in advanced manufacturing, bioscience, or research and development. Eligible incentives under the MEGA Program include the following:
- An investment tax credit of up to 5.0% of the business’s qualifying investment.
- A refund of the sales and use taxes paid for gas, electricity, water, and sewer utility services; tangible personal property; or services rendered, furnished, or performed that contributed to the construction or equipping of the facility.
- A withholding tax credit of up to 3.0% of the gross wages paid to each employee in a project job that pays at least the qualifying wage threshold.
Tax incentives under the MEGA Program cannot currently be awarded for more than two eligible businesses or after January 1, 2027.
Businesses associated with foreign adversaries cannot participate in the MEGA Program. As of February 4, 2026, “foreign adversary” as defined in 15 C.F.R. §7.4(a) and 15 C.F.R. §791.4 includes the following:
- China
- Cuba
- Iran
- North Korea
- Russia
- Venezuelan politician Nicolás Maduro
Assumptions
- It is assumed that extending the end of the MEGA Program from January 1, 2027, to January 1, 2030, will result in one additional award.
- The IEDA will allocate the full amount of the award in the first year of the project, but claims will not be made until three years after the award is granted, upon project completion.
- The full amount of the award will be made for each of the tax credits authorized under the MEGA Program, and all credits will be fully refunded rather than carried forward against future tax liability.
- All tax credits will be remitted in the same year they are claimed.
- A qualifying investment under the MEGA Program will be $1.000 billion.
- A total of 25.0% of the project investment will be subject to sales tax and a sales tax refund.
- Secure an Advance Vision for Education (SAVE) refunds are 1.0% of taxable expenditures.
- The requirement for 50.0% of jobs created to be eligible to receive a withholding tax credit will be met in the first year of the project completion.
- Wages will increase by 3.0% each year.
Fiscal Impact
Division II of the Bill is estimated to decrease revenue to the General Fund and the SAVE Fund over the five-year life of an award by the amounts shown in Figure 1.
Figure 1 — Fiscal Impact of Division II (in Millions)
General Fund SAVE
FY 2030 $ -18.0 $ -0.5 FY 2031 -18.2 -0.5 FY 2032 -18.3 -0.5 FY 2033 -18.5 -0.5 FY 2034 -18.7 -0.5 Division III — Business Incentives for Growth Program Training Fund
Description
Division III of the Bill establishes the Business Incentives for Growth (BIG) Program Training Fund (Training Fund) under the control of the IEDA. The Training Fund is required to be used to reimburse certain training expenses incurred by a business for a project under the BIG Program.
The Training Fund receives funding from the withholding of income tax as specified in Iowa Code section 422.16. An amount up to 1.5% of the gross wages that a business pays to employees included under a BIG Program agreement is diverted from income tax withholding and deposited into the Training Fund.
Background
The BIG Program was created in 2025 Iowa Acts, chapter 136 (Economic Development Programs and Credits Act), as a successor to the High Quality Jobs (HQJ) Program. The BIG Program provides tax incentives, which are subject to award caps, and financial assistance, which is appropriated by the General Assembly.
Assumptions
- The number of jobs created and retained under the BIG Program will be comparable to the number of jobs created and retained under the HQJ Program in FY 2025.
- Business Incentives for Growth Program agreements will last for three years.
- The qualifying wage for participation in the BIG Program is the same as the qualifying wage for participation in the HQJ Program. Wages and qualifying wages are assumed to increase by 3.0% each year.
- Jobs included in a BIG Program agreement will be created at the beginning of the fiscal year following an award.
- Income tax withholding diverted to the Training Fund will begin in the fiscal year following the award.
Fiscal Impact
Division III of the Bill is estimated to decrease revenue to the General Fund and increase revenue to the BIG Program Training Fund by the amounts shown in Figure 2. Figure 2 — Fiscal Impact of Division III (in Millions)
General Fund BIG Program Training Fund
FY 2027 $ -0.8 $ 0.8 FY 2028 -1.6 1.6 FY 2029 -2.5 2.5 FY 2030 -2.6 2.6 FY 2031 -2.7 2.7 Division IV — Repeal of the New Jobs Tax Credit
Description
Division IV of the Bill repeals the New Jobs Tax Credit against personal income and corporate income taxes. The Division is effective upon enactment.
Background
The New Jobs Tax Credit allows a credit against individual and corporate income taxes of up to 6.0% of unemployment insurance taxable wages for new jobs created as a result of the Iowa New Jobs Training (260E) Program. The unemployment insurance taxable wage for calendar year (CY) 2026 is $20,400, which means the New Jobs Tax Credit could be claimed for a maximum of $1,224 for each new job created as a result of the 260E Program. The New Jobs Tax Credit can only be claimed once for each eligible new job.
Assumptions
- Based on historical claims data, it is assumed that New Jobs Tax Credit claims are equal to 1.79% of the New Jobs Withholding Credit and the Supplemental New Jobs Credit.
- Assumptions for New Jobs Withholding Credit and the Supplemental New Jobs Credit are outlined in Division VI of the Fiscal Note.
Fiscal Impact
Division IV of the Bill is estimated to increase revenue to the General Fund by the following amounts:
- FY 2027 = $14,000
- FY 2028 = $71,000
- FY 2029 = $145,000
- FY 2030 = $216,000
- FY 2031 = $287,000
- FY 2032 = $365,000
- FY 2033 = $434,000
- FY 2034 = $482,000
- FY 2035 = $511,000
- FY 2036 = $525,000
- FY 2037 and beyond = $528,000
Division V — Load Forecasting
Description
Division V of the Bill requires the IEDA to commission the Iowa State University of Science and Technology (ISU) to produce a load forecasting report on the probable future growth of the use of electricity in Iowa and the Midwest region every two years.
The Division grants the Utilities Commission the authority to compel all public utilities to share with ISU the information necessary to develop State load forecasts and State electric transmission system expansion planning analyses.
The Division creates the Electric Transmission System Expansion Plans Analysis and Load Forecasting Fund (Fund) under the control of the IEDA. All electric utilities are required to remit to the Fund up to 0.02% of the total gross operating revenues during the last calendar year derived from the utilities’ intrastate public utility operations. The Utilities Commission is required to establish a maximum amount of remittances in aggregate and provide a schedule for remittances paid by electric utilities into the Fund in administrative rules. The Fund is under the authority of the IEDA for the load forecasting report. The Bill exempts the Fund from reversion requirements and allows the Fund balance to carry forward to the next year. The Fund is allowed to retain any interest or earnings on the Fund balance.
Background
According to Iowa’s Electric Profile, in CY 2024, there were 182 electric utilities that provided 54.9 million megawatt hours (MWh) of electricity to 1.7 million Iowa customers.
Assumptions
- The load forecasting report created by ISU will be substantially similar to the Indiana Electricity Projections report created by the State Utility Forecasting Group at Purdue University.
- The amount collected from electric utilities and deposited into the Fund will be less than 0.02% of the total gross operating revenues during the previous calendar year derived from the utilities’ intrastate public utility operations.
- Preparation for the first biennial load forecasting report will occur between January 1, 2027, and December 31, 2028. Preparation for each biennial report thereafter will occur between January 1 and December 31 of the year of publication.
- Preparation for the load forecasting report will require the following full-time equivalent (FTE) positions:
- 0.9 Division Director FTE position
- 0.9 Senior Research Analyst FTE position
- 0.9 Research Analyst 3 FTE position
- 0.9 Research Analyst 2 FTE position
- 0.9 Research Analyst 1 FTE position
Fiscal Impact
Division V of the Bill is estimated to require an additional 4.5 FTE positions under ISU during the preparation of the load forecasting report and result in the following amounts being remitted by electric utilities to the Fund for the report:
- FY 2027 = $244,000
- FY 2028 = $489,000
- FY 2029 and beyond = $244,000
Division VI — Iowa Industrial New Jobs Training Program
Description
Division VI of the Bill does the following:
- Provides that community colleges cannot extend 260E agreements entered into on or before June 30, 2026.
- Provides that payments for 260E Program costs cannot be deferred for more than seven years for agreements entered into on or after July 1, 2026.
- Prohibits a bond issued by a community college for a project from exceeding 70.0% of total program costs related to training expenses.
- Prohibits 260E Program costs from including travel, conference, or legal fee reimbursements.
- Limits community college administrative expenses to 15.0% of 260E Program costs.
- Requests the Legislative Council to establish an interim study committee during the 2026 Legislative Session to review and make recommendations regarding the 260E Program. The interim study committee must hold its first meeting on or before August 1, 2026, and must submit a report detailing the committee’s findings and recommendations to the General Assembly no later than December 15, 2026.
Background
Under the 260E Program, a participating business partners with a community college, which sells bonds to finance the cost of newly established training. The business diverts 1.5% of gross payroll from the State withholding taxes generated by the new positions to the community college to retire the bonds. Participating businesses must remit payments to the community college before making claims to the withholding tax credit.
After the training obligation of a business under the 260E Program has been paid off, an amount equal to the withholding payments is credited to the Workforce Development Fund (WDF) Account for 10 years, up to a maximum of $7.8 million annually. Moneys in the WDF Account are appropriated to Iowa Workforce Development (IWD) under Iowa Code section 84G.3 to be used for apprenticeship training and job training.
Assumptions
- In FY 2025, $29.5 million in withholding tax credits was awarded under the New Jobs Withholding Tax Credit and the Supplemental New Jobs Tax Credit. It is assumed that future awards under current law would be at FY 2025 levels.
- The initial fiscal impact for claims under the Bill will occur in FY 2027.
- The cost of employee training and the number of employees trained under the 260E Program will remain at FY 2025 levels.
- Bonds issued to community colleges will be for 70.0% of total program costs. The remaining 30.0% of program costs will be provided by participating businesses.
- Limiting bond issuances to 70.0% of program costs will decrease 260E Program withholding payments from businesses to community colleges by 30.0% and decrease tax credit claims on those payments by 30.0%.
- Total program costs include bond interest payments.
- Tax credits under the 260E Program are based on the gross wages of employees receiving training. The gross wages of employees receiving training are not impacted by the Bill.
- Tax credits under the 260E Program cease when all bond principal and interest have been paid.
- Current community college administrative expenses are 19.5% of bond par values.
- Direct bond issuance fees do not include legal fees.
- Based on historical claim data, it is assumed that 100.0% of tax credits will be claimed, with the timing of claims under current law indicated below:
- Year 0 = 2.7%
- Year 1 = 10.7%
- Year 2 = 14.0%
- Year 3 = 13.5%
- Year 4 = 13.5%
- Year 5 = 14.6%
- Year 6 = 13.1%
- Year 7 = 9.2%
- Year 8 = 5.4%
- Year 9 = 2.6%
- Year 10 = 0.7%
Fiscal Impact
Division VI of the Bill is estimated to increase revenue to the General Fund by the following amounts:
- FY 2027 = $15,000
- FY 2028 = $75,000
- FY 2029 = $154,000
- FY 2030 = $230,000
- FY 2031 = $306,000
- FY 2032 = $388,000
- FY 2033 = $4.0 million
- FY 2034 = $6.7 million
- FY 2035 = $8.3 million
- FY 2036 = $9.0 million
- FY 2037 and beyond = $9.2 million
Fiscal Impact Summary
House File 2799 is estimated to increase and decrease the amount of funds available for various funds and programs as shown in Figures 3 and 4.
Figure 3 — General Fund Fiscal Impact of House File 2799 (in Millions) FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 Division I $ 0.0 $ -1.8 $ -1.9 $ -3.9 $ -2.0 Division II 0.0 0.0 0.0 -18.0 -18.2 Division III -0.8 -1.6 -2.5 -2.6 -2.7 Division IV 0.0 0.1 0.1 0.2 0.3 Division VI 0.0 0.1 0.2 0.2 0.3 Total $ -0.8 $ -3.3 $ -4.1 $ -24.0 $ -22.2 Figure 4 — Other Funds Fiscal Impact of House File 2799 (in Millions) FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 Division II - SAVE Fund $ 0.0 $ 0.0 $ 0.0 $ -0.5 $ -0.5
Division III - BIG Program
Training Fund
0.8 1.6 2.5 2.6 2.7
Division V - Load Forecasting
Fund
0.2 0.5 0.2 0.2 0.2
Sources
- Iowa Department of Revenue
- Iowa Economic Development Authority
- Iowa Economic Development Authority financial assistance reports
- Purdue University State Utility Forecasting Group
- Iowa Utilities Commission reports
- Harvard Business School
- State Accounting System
- Legislative Services Agency calculations
- Final Fiscal Note — Economic Development, Tax Credit Programs and Load Forecasting · 19 de mayo de 2026
- Economic Development, Tax Credit Programs and Load Forecasting · 2 de mayo de 2026
- Economic Development, Tax Credit Programs and Load Forecasting · 2 de mayo de 2026
Lo que cambia del Código de Iowa (Iowa Code)
Crea§15.120A§15.512§15.600§15.601§15.602§15.603§15.604§15.605§15.606§260E.8§422.12R§476.10C
Modifica§15.491§15.501§2.48§260E.3§260E.7§422.10§422.33§422.60§476.1A§476.1B§476.2
Deroga§422.11A
Cita§533.329
Cabildeo
11 a favor · 6 en contra · 32 indecisos · Quiénes →