Bills › 90th General Assembly
Relating to electric power generating facility emission plans and projects, and including effective date and applicability provisions
Sponsored by the Senate Commerce Committee
Where it is now
- Done: IntroducedJanuary 17, 2023
- Done: SubcommitteeJanuary 17, 2023
- Done: Senate committeeFebruary 2, 2023
- Done: Passes the SenateMarch 22, 202341–9
- Skipped: House committeeSkipped
- Done: Passes the HouseFebruary 15, 202375–24
- Done: To the GovernorApril 28, 2023
- Done: Signed into lawApril 28, 2023
HF 248 became law → The same legislation passed as HF 248, so this version was set aside. Go to HF 248 What’s a funnel?
What’s in it
AI summary Coal-powered electricity plants in Iowa can now create or update their own multiyear plans and budgets for managing emissions. Instead of following strict filing deadlines, these facilities can choose when to submit updates to their plans. They also have the option to ask for early approval for projects meant to reduce pollution.1
Read the official explanation
This bill relates to electric power generating facility emission plans, updates, and budgets. The bill allows electric power generating facilities fueled by coal and located in Iowa to develop a reasonably cost-effective multiyear plan and budget or update an existing plan and budget for managing emissions. Current law requires electric power generating facilities fueled by coal and located in Iowa on July 1, 2001, to develop a cost-effective multiyear plan and budget for managing emissions. The bill removes provisions requiring plans and budgets to be filed with the utilities board by April 1, 2002, and updates filed at least every months thereafter. The bill provides that an electric power generating facility located in the state has the discretion to file an update to a multiyear plan. Additionally, the plan may seek advanced review and approval for pollution and emission-related projects. The bill provides that an application for advanced review shall be submitted by a rate-regulated public utility before the anticipated start of a pollution and emission-related project. An operator of an electric power generating facility that is owned by two or more regulated public utilities may file an application on behalf of all of the rate-regulated public utility owners. The bill takes effect upon enactment. The bill applies to electric power generating facility emissions plans or updates filed on or after the effective date of the bill.
Changed since by amendment S-3095; see Amendments.
Senate subcommittee
Named January 17, 2023 (as SSB 1043). On January 19, 2023 it recommended passage. [].
Three legislators hear a bill first and recommend what the committee should do; it’s the best time to weigh in. How to take part
Family tree
Study bill
90th General Assembly